Province | Subbasin | % |
---|---|---|
Basinwide | - | 100.00% |
Previous: | Next: |
---|---|
46273 REL 52: 1983-319-00 EXP NEW MARKING & MONITORING TECH |
|
* Expenditures data includes accruals and are based on data through 31-Dec-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Funding Package - Submit draft to COTR | A: 119. Administration tasks for this project | 08/31/2014 | 02/25/2015 | |
Environmental compliance documentation | B: 165. Environmental compliance review for PIT Tag and in-stream systems | 03/31/2014 | 03/31/2014 | |
Delivery of final ogee transceivers | C: 156. Spillway PIT-tag system - development, evaluation, equipment | 01/31/2015 | 03/30/2015 | |
Data will be collected from research conducted on in-stream interrogation systems | D: 156. Continue development of in-stream interrogation systems | 01/31/2015 | 01/31/2015 | |
Attach Progress Report in Pisces | E: 132. Progress Report for Proj 1983-319-00 covering (Dec 1, 2011) to (Dec 31, 2012) | 05/15/2014 | ||
Attach Progress Report in Pisces | F: 132. Combined Progress Report for the period (Jan 1, 2013) to (Dec 31, 2013) | 07/15/2014 | ||
BiOp RME Report completed for CY 13 | G: 141. RPA Reports for CY13 | 03/15/2014 | 05/23/2014 | |
Final (postable) version Distribute Progress Report | I: 132. Added: Progress Report for Proj 2001-003-00 covering (Jan 2010) to (Dec 2012) | 03/31/2015 | ||
Distribute Progress Report | J: 132. Added: Progress Report for Proj 1983-319-00 covering (Dec 1, 2011) to (Dec 31, 2012) | 03/31/2015 | ||
Distribute Progress Report for External Review to [Insert external review entity] | K: 132. Added: Combined Progress Report for the period (Jan 1, 2013) to (Dec 31, 2013) | 03/31/2015 | ||
Data from the evaluation of the network of interrogation systems for adult salmonids | L: 162. Added: Evaluate performance of the entire network of adult interrogation systems | 03/31/2015 | 03/31/2015 | |
Data from the evaluation of new PIT-tag technologies (tags and transceivers) | M: 157. Added: Evaluation of a new PIT-tag technologies (tags and transceivers) | 03/31/2015 | 03/31/2015 | |
Analysis of the data collected from the fish, field, and laboratory tests conducted in 2014 | N: 162. Added: Analyze results from fish, field, and laboratory tests used to evaluate PIT-tag technologies | 03/31/2015 | ||
Submit BiOp RPA Report in Taurus for CY14 | O: 141. Added: RPA report for CY2014 | 03/15/2015 | 03/15/2015 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (Oncorhynchus tshawytscha) - All Populations |
|
Coho (Oncorhynchus kisutch) - Lower Columbia River ESU (Threatened) |
|
Coho (O. kisutch) - Unspecified Population |
|
Sockeye (Oncorhynchus nerka) - All Populations |
|
Steelhead (Oncorhynchus mykiss) - All Populations |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 119 | Administration tasks for this project | 02/01/2014 | ||||||
B | 165 | Environmental compliance review for PIT Tag and in-stream systems | 02/01/2014 | ||||||
C | 156 | Spillway PIT-tag system - development, evaluation, equipment | 11/07/2013 | ||||||
D | 156 | Continue development of in-stream interrogation systems | 11/07/2013 | ||||||
E | 132 | Progress Report for Proj 1983-319-00 covering (Dec 1, 2011) to (Dec 31, 2012) | 02/01/2014 | ||||||
F | 132 | Combined Progress Report for the period (Jan 1, 2013) to (Dec 31, 2013) | 02/01/2014 | ||||||
G | 141 | RPA Reports for CY13 | 02/01/2014 | ||||||
H | 185 | Periodic Status Reports for BPA | 02/01/2014 | ||||||
I | 132 | Added: Progress Report for Proj 2001-003-00 covering (Jan 2010) to (Dec 2012) | 02/01/2014 | ||||||
J | 132 | Added: Progress Report for Proj 1983-319-00 covering (Dec 1, 2011) to (Dec 31, 2012) | 02/01/2014 | ||||||
K | 132 | Added: Combined Progress Report for the period (Jan 1, 2013) to (Dec 31, 2013) | 02/01/2014 | ||||||
L | 162 | Added: Evaluate performance of the entire network of adult interrogation systems | 02/01/2014 | ||||||
M | 157 | Added: Evaluation of a new PIT-tag technologies (tags and transceivers) | 02/01/2014 | ||||||
N | 162 | Added: Analyze results from fish, field, and laboratory tests used to evaluate PIT-tag technologies | 02/01/2014 | ||||||
O | 141 | Added: RPA report for CY2014 | 02/01/2014 |